We redevelop the
Bernauer Heerstraße 54 – 60 in Eberswalde
Number of living spaces: 117 > 109
Types of housing: Single apartment, 2-person shared apartment, 3-person shared apartment
Last renovation: 1998
Start of renovation: March 2022, with rise 60
Planned completion: September 2025
Planned renovation costs: approx. 5 million euros, financing from own funds
Measures: Renovation in 4 construction phases according to staircases; completely renew technical building equipment, upgrade fire protection, adapt floor plans to suit needs, renovate sanitary facilities, kitchen and living areas, furnish rooms, renew roofing, modernize facade, create 2 wheelchair-accessible living spaces, relocate 1 janitor’s office, create indoor and outdoor meeting place for students.
NEW: Extension of measures with the help of the Brandenburg packagein prospect: Install photovoltaic system and solar thermal system
NEW: estimated cost extension: approx. 120,000 euros, financing from non-repayable state funds
It is important to note that the residents of this residential complex have voiced criticism of the plans for the redesign. The main point of criticism is the planned dissolution of the previous 3-person shared flats. In a transparent and ongoing exchange with the residents, measures and approaches on the part of our work could be brought closer and as a result, after examining all possibilities, the original plans for the staircases 56 and 58 were changed, so that the residential structure of the 3-person shared flats in two staircases remains.